NEW QUESTION # 65
In order to be defined as an issue, which of the following conditions must be satisfied?
- A. It must have happened because of an identified risk.
- B. It must result in a set tolerance being exceeded.
- C. The project team must be able to deal with it internally.
- D. The project manager must be able to resolve it.
Answer: B
NEW QUESTION # 66
Communication includes:
1) exchanging information
2) managing stakeholders
3) confirming there is a shared understanding
4) building relationships within your team
- A. 2 and 4 only
- B. 1 and 4 only
- C. 2 and 3 only
- D. 1 and 3 only
Answer: D
NEW QUESTION # 67
Which of the following would be considered as a valid objective for the post project review?
- A. Improve future estimating accuracy.
- B. Plan how to complete the objectives of the project.
- C. Plan the next project for the project team.
- D. Make proposals for the operation of the project deliverables.
Answer: A
NEW QUESTION # 68
Which of the following statements about the business case is true?
- A. The business case contains key information on how the project will be performed.
- B. The business case should always be referred to throughout the project
- C. The business case becomes the project manager's responsibility, once the project is in the implementation phase.
- D. The business case once written will never change.
Answer: B
NEW QUESTION # 69
What action can lead to more consistent communication in the project?
- A. Communication is planned in advance and all messages delivered use the approved framework.
- B. Only transmitting information that stakeholders have requested, ensuring that any excess information is kept to a minimum.
- C. Communication is carried out en-masse ensuring that all stakeholders get all information.
- D. Communicating information on a one-way basis reducing the need for stakeholders to waste their time providing feedback
Answer: A
NEW QUESTION # 70
What is the likely decision to arise from the response stage of the risk management process?
- A. Whether the process being used is robust enough for the project being undertaken.
- B. Whether to proceed with the project or recommend termination.
- C. Whether to use brainstorming or a workshop to decide on the best response.
- D. Whether to proactively invest to bring the exposure to risk within tolerable levels.
Answer: D
NEW QUESTION # 71
Quality management ensures that ______ are fit for purpose.
- A. standards and benefits.
- B. managers and teams.
- C. processes and outputs.
- D. regulations and requirements.
Answer: C
NEW QUESTION # 72
One of the benefits of developing communication plans in projects is that this ensures:
- A. your message is understood.
- B. clear reporting lines for the project.
- C. that all communication is delivered face to face.
- D. the power and influence of stakeholders is understood.
Answer: A
NEW QUESTION # 73
Which statement regarding the purpose of the business case would be the most true?
- A. It will determine which stakeholders are most eligible to become members of the steering group,
- B. It will be referred to throughout the project in order to make decisions about the continuing viability of the project.
- C. It will act as a reference for the project team regarding the specific. processes to be used for project delivery.
- D. Once agreed the business case will become the baseline by which the project will be deployed,
Answer: B
NEW QUESTION # 74
Which of the following can be adjusted in a timebox situation?
- A. Time and cost.
- B. Deadline and duration.
- C. Budget and resources.
- D. Scope and quality.
Answer: D
NEW QUESTION # 75
During project deployment, which process will provide confidence that the project will satisfy the relevant quality standards?
- A. Total quality management (TQM).
- B. Strategic Business Planning for Quality (SBPQ).
- C. Total quality planning.
- D. Quality assurance for the project.
Answer: D
NEW QUESTION # 76
The group whose remit is to set the strategic direction of a project is commonly known as:
- A. steering group.
D supplier group. - B. the project management team.
- C. primary user group.
Answer: A
NEW QUESTION # 77
Which of the following role is primarily responsible for defining goals and creating vision for the operability of the project's outputs?
- A. User.
- B. Product owner.
- C. Project sponsor
Answer: B
Explanation:
D Business case owner.
NEW QUESTION # 78
Which one of the following statements about the project life cycle is true?
- A. The project budget is divided equally between each phase of the project life cycle.
- B. The project life cycle has a number of distinct phases.
- C. The same processes are used in each of the project life cycle phases.
- D. The phases in the project life cycle are always the same size.
Answer: B
NEW QUESTION # 79
Configuration management could best be described as:
- A. the process through which all requests to change the approved baseline of a project is captured.
evaluated and then approved. rejected or deferred. - B. the system that ensures that all changes to configuration items are controlled and the interrelationships between items are identified.
- C. the technical and administrative activities concerned with the creation, maintenance, controlled change and quality control of the scope of work.
- D. A report of the current status and history of all changes to the configuration, together with a complete record of what has happened to the configuration to date.
Answer: C
NEW QUESTION # 80
If using an iterative life cycle what actions might be necessary for scope items that are NOT considered as 'must have'?
- A. They would sacrificed if at any time Was to go over budget or be late
- B. They need to be given a special priority to ensure that they are definitely delivered.
- C. They should have best resort to ensure they efficiently delivered.
- D. The project could be If the delivery of these requirements were proving more difficult than expected
Answer: A
NEW QUESTION # 81
Stakeholder analysis supports effective stakeholder engagement by:
- A. identifying stakeholders with high levels of power and interest.
- B. ensuring stakeholder acceptance of project deliverables.
- C. providing information to all stakeholders.
- D. justifying the preferred project option to stakeholders.
Answer: A
NEW QUESTION # 82
......
APM APM-PFQ Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
| Topic 4 |
|
| Topic 5 |
|
| Topic 6 |
|
| Topic 7 |
|
| Topic 8 |
|
| Topic 9 |
|
APM-PFQ Actual Questions Answers PDF 100% Cover Real Exam Questions: https://www.vce4plus.com/APM/APM-PFQ-valid-vce-dumps.html
APM-PFQ Exam questions and answers: https://drive.google.com/open?id=13a5AcKcoCgzyeixkULlIfC--qKi4ND9n