NEW QUESTION # 65
In order to be defined as an issue, which of the following conditions must be satisfied?

  • A. It must have happened because of an identified risk.
  • B. It must result in a set tolerance being exceeded.
  • C. The project team must be able to deal with it internally.
  • D. The project manager must be able to resolve it.

Answer: B


NEW QUESTION # 66
Communication includes:
1) exchanging information
2) managing stakeholders
3) confirming there is a shared understanding
4) building relationships within your team

  • A. 2 and 4 only
  • B. 1 and 4 only
  • C. 2 and 3 only
  • D. 1 and 3 only

Answer: D


NEW QUESTION # 67
Which of the following would be considered as a valid objective for the post project review?

  • A. Improve future estimating accuracy.
  • B. Plan how to complete the objectives of the project.
  • C. Plan the next project for the project team.
  • D. Make proposals for the operation of the project deliverables.

Answer: A


NEW QUESTION # 68
Which of the following statements about the business case is true?

  • A. The business case contains key information on how the project will be performed.
  • B. The business case should always be referred to throughout the project
  • C. The business case becomes the project manager's responsibility, once the project is in the implementation phase.
  • D. The business case once written will never change.

Answer: B


NEW QUESTION # 69
What action can lead to more consistent communication in the project?

  • A. Communication is planned in advance and all messages delivered use the approved framework.
  • B. Only transmitting information that stakeholders have requested, ensuring that any excess information is kept to a minimum.
  • C. Communication is carried out en-masse ensuring that all stakeholders get all information.
  • D. Communicating information on a one-way basis reducing the need for stakeholders to waste their time providing feedback

Answer: A


NEW QUESTION # 70
What is the likely decision to arise from the response stage of the risk management process?

  • A. Whether the process being used is robust enough for the project being undertaken.
  • B. Whether to proceed with the project or recommend termination.
  • C. Whether to use brainstorming or a workshop to decide on the best response.
  • D. Whether to proactively invest to bring the exposure to risk within tolerable levels.

Answer: D


NEW QUESTION # 71
Quality management ensures that ______ are fit for purpose.

  • A. standards and benefits.
  • B. managers and teams.
  • C. processes and outputs.
  • D. regulations and requirements.

Answer: C


NEW QUESTION # 72
One of the benefits of developing communication plans in projects is that this ensures:

  • A. your message is understood.
  • B. clear reporting lines for the project.
  • C. that all communication is delivered face to face.
  • D. the power and influence of stakeholders is understood.

Answer: A


NEW QUESTION # 73
Which statement regarding the purpose of the business case would be the most true?

  • A. It will determine which stakeholders are most eligible to become members of the steering group,
  • B. It will be referred to throughout the project in order to make decisions about the continuing viability of the project.
  • C. It will act as a reference for the project team regarding the specific. processes to be used for project delivery.
  • D. Once agreed the business case will become the baseline by which the project will be deployed,

Answer: B


NEW QUESTION # 74
Which of the following can be adjusted in a timebox situation?

  • A. Time and cost.
  • B. Deadline and duration.
  • C. Budget and resources.
  • D. Scope and quality.

Answer: D


NEW QUESTION # 75
During project deployment, which process will provide confidence that the project will satisfy the relevant quality standards?

  • A. Total quality management (TQM).
  • B. Strategic Business Planning for Quality (SBPQ).
  • C. Total quality planning.
  • D. Quality assurance for the project.

Answer: D


NEW QUESTION # 76
The group whose remit is to set the strategic direction of a project is commonly known as:

  • A. steering group.
    D supplier group.
  • B. the project management team.
  • C. primary user group.

Answer: A


NEW QUESTION # 77
Which of the following role is primarily responsible for defining goals and creating vision for the operability of the project's outputs?

  • A. User.
  • B. Product owner.
  • C. Project sponsor

Answer: B

Explanation:
D Business case owner.


NEW QUESTION # 78
Which one of the following statements about the project life cycle is true?

  • A. The project budget is divided equally between each phase of the project life cycle.
  • B. The project life cycle has a number of distinct phases.
  • C. The same processes are used in each of the project life cycle phases.
  • D. The phases in the project life cycle are always the same size.

Answer: B


NEW QUESTION # 79
Configuration management could best be described as:

  • A. the process through which all requests to change the approved baseline of a project is captured.
    evaluated and then approved. rejected or deferred.
  • B. the system that ensures that all changes to configuration items are controlled and the interrelationships between items are identified.
  • C. the technical and administrative activities concerned with the creation, maintenance, controlled change and quality control of the scope of work.
  • D. A report of the current status and history of all changes to the configuration, together with a complete record of what has happened to the configuration to date.

Answer: C


NEW QUESTION # 80
If using an iterative life cycle what actions might be necessary for scope items that are NOT considered as 'must have'?

  • A. They would sacrificed if at any time Was to go over budget or be late
  • B. They need to be given a special priority to ensure that they are definitely delivered.
  • C. They should have best resort to ensure they efficiently delivered.
  • D. The project could be If the delivery of these requirements were proving more difficult than expected

Answer: A


NEW QUESTION # 81
Stakeholder analysis supports effective stakeholder engagement by:

  • A. identifying stakeholders with high levels of power and interest.
  • B. ensuring stakeholder acceptance of project deliverables.
  • C. providing information to all stakeholders.
  • D. justifying the preferred project option to stakeholders.

Answer: A


NEW QUESTION # 82
......


APM APM-PFQ Exam Syllabus Topics:

TopicDetails
Topic 1
  • Understand Communication in the Context of a Project: The topic focuses on the advantages and disadvantages of different communication methods.
Topic 2
  • Understand the Roles and Responsibilities within Projects: The topic focuses on project management roles and responsibilities. Moreover, the topic covers roles such as the project sponsor, project manager, project governance, project team members, and end users.
Topic 3
  • Understand Project Management and the Operating Environment: It includes defining the term project and stating the differences between a project and business as usual. It also covers defining 'project management' and its key purpose.
Topic 4
  • Understand Resource, Scheduling, and Optimisation in a Project: This topic delves into the purpose of scheduling, critical path analysis, and milestones. It also defines the term time boxing.
Topic 5
  • Understand Leadership and Teamwork within a Project: This topic defines the term leadership and explains how a project team leader can influence team performance.
Topic 6
  • Understand Project Risk and Issue Management in the Context of a Project: The topic defines the term risk and explains the purpose of risk management. It outlines the stages of a typical risk management process. It also describes the use of risk registers.
Topic 7
  • Understand Project Management Planning: This topic explains how the deployment baseline differs between linear and iterative life cycles. Additionally, the topic outlines the stakeholders of a project management plan, the purpose, and the typical content of a business case.
Topic 8
  • Understand Quality in the Context of a Project: This topic defines the term quality and outlines the purpose of quality management. It also includes defining quality planning.
Topic 9
  • Understand Project Scope Management: It defines scope management. Moreover, the topic focuses on the distinction between iterative and linear project scope management.

 

APM-PFQ Actual Questions Answers PDF 100% Cover Real Exam Questions: https://www.vce4plus.com/APM/APM-PFQ-valid-vce-dumps.html

APM-PFQ Exam questions and answers: https://drive.google.com/open?id=13a5AcKcoCgzyeixkULlIfC--qKi4ND9n